Project Description
The proposed dam will traverse the
Punta-taytay creek to impound water for the dry months
starting in January. The water stored will be used to
support a third crop, theoretically the highest yielding
because of longer days allowing photosytesis if water is
available. The dam will be 10 linear meter long.
 |
| Punta-taytay creek 10Km south
of Bacolod City where the proposed impounding dam
is to be built. The dam shall be built 200 meters
east of the National Highway from the
Punta-taytay Bridge in Bangga Ramos.
"Ramos Stop ." |
 |
| The ricefields during the
rainy months that will benefit from stored water
if the impounding dam is constructed. |
It is also designed to
prevent sea water entering the creek from Guimaras Strait
during high tides to mix with irritation water even
during the wet season should farmers require use of
pumped water.
The project should help some 50 farmers
and irrigate 50 hectares as it catches the run-off waters
from the main irrigation canals of the upper Bago River.
Project Design





Project Cost
MICRO-asia
BUILDERS CORPORATION
LOT 6, BLOCK 19 GARDENVILLE
SUBDIVISION
TANGUB, BACOLOD CITY
DETAILED
ESTIMATE
|
Project
Owner
Location
Date
Subject |
:
:
:
:
: |
OVERFLOW DAM
Summary of Estimate for Ten(10)
Linear Meter Overflow Dam |
|
Mixing
Sand
Mixing Gravel
Cement
Rebars
12 mm X 6m
Concrete Culvert
0.60 X 1m
Forms and Scaffolding
2" X 2" X 10' Cocolumber
¼ X 4' X 8' Ordinary Plywood
Common Nails
Selected Boulders
Sub-Total
Miscellanous
Contingencies
Construction Cost per linear meter
Total (P6,455.00 X 10M.)
|
=
=
=
=
=
=
=
=
=
= |
0.763m³
1.50m³
14 bags
4 lenght
1 ea
8 lenght
2 pcs
1 kilo
2 cu. Yard |
@
@
@
@
@
@
@
@
@ |
P250.00 =
P350.00 =
P100.00 =
P60.00 =
P380.00 =
P35.00 =
P250.00 =
P40.00 =
P300.00 =
|
P190.75
525.00
1,400.00
240.00
380.00
280.00
500.00
40.00
600.00
P4,155.00
1800.00
500.00
6,455.00
P64,550.00
P64,550.00 |
| Add: Cooperative Development
& Registration (seminars, legal etc.) TOTAL PROJECT COST
|
35,450.00
P
100,000.00
=========
|
|
|